5
This quarter
3
$4.4M pending value
+$4.4M
If all pending approved
5.2d
Target: 5.0d
Cable Tray Rerouting - Level 3
Critical path impact required expedited approval. Design change validated by str...
Cooling Tower Specification Change
Value engineering study found $1.8M savings with current design. Existing specif...
Fire Suppression Upgrade - Zone A
Required to meet updated fire code. Non-compliance would delay occupancy permit.
Foundation Depth Extension
Geotechnical survey revealed unstable soil at planned depth. Extension necessary...
Electrical Panel Relocation
Vendor quote 40% above historical benchmark. Requested re-quote from alternative...