Are we hitting our gates?
9
Upcoming milestones
1
Critical path impacted
3
29d total slip
45%
Avg criteria met
Structural Steel Complete
Henderson -- West
04-28
05-10
Gates 2/4
Mechanical Rough-in Complete
Mesa -- Southeast
05-18
05-24
Gates 3/5
Underground Utilities Complete
Pryor Creek -- Central
05-22
Gates 2/3
Foundation Pour Complete
Papillion -- Central
05-15
Gates 3/4
Easement Resolution
De Soto -- Central
05-01
05-12
Gates 0/2
Site Grading Complete
New Albany -- Southeast
05-20
Design Review Complete
Storey County -- West
05-25
Permitting Submission
Midlothian -- Northeast
05-28
Gates 1/3
Electrical Rough-in Complete
06-10
06-22
Gates 0/4