62 of 87 projects within target
avg over target
avg over target
87
Active
62
On Track
25
At Risk
Top Outliers
Top Outliers
Top Outliers
Top Outliers
On Track / At Risk / Critical distribution
Schedule performance tracking across all regions. Target is 75% or higher for "On Track" status. This report monitors FDOB schedule adherence and highlights areas requiring attention.
Source: FDOB Schedule Performance Tracker (Weekly refresh) · odc_fdob_schedule_metrics. All data audit-logged.
Projects exceeding variance thresholds
| Project | Region | PGM | Design Var | CA Var | Narrative |
|---|---|---|---|---|---|
| ARA-Hub1-1&2 | NA-West | Lisa McIntyre | +4.2m | +1.1m | Design stopped and redesigned |
| KNC-Hub2-1&3 | NA-West | Lisa McIntyre | +3.8m | +0.4m | AE PO Delay & RFP delay |
| STB-Hub1-1 | EMEA | Paul Cahill | +5.1m | +0.8m | Major Permitting Delays in Jurisdiction |
| KAS-Hub1-1&2 | NA-West | Loren Smith | +2.9m | +0.6m | Enlarger Kitchen Cut delay |
| VLB-Hub2-1 | EMEA | Sarah Connor | +4.7m | +0.2m | Land acquisition delay |
| WES-Hub1-2 | EMEA | Paul Cahill | +3.9m | +0.5m | Environmental impact assessment extended |
| MNK-Hub2-1 | APAC | Wei Chen | +3.1m | +0.4m | Typhoon season delay |
| SGR-Hub1-1 | NA-East | Mike Torres | +2.6m | +0.3m | Utility easement negotiation |